Constructing Lorestan petrochemical Above Ground and underground piping Operations:
Constructing around 550,000 ID pipes welding , around 150,000 ID UG pipes welding and Constructing around 50,000 inch-meters AG and UG threaded piping , Constructing around 650 tone support , Constructing around 300,000 m2 sandblast and coloring piping equipment and 4500 tone structures and Constructing around 50,000 m2 hot and cold insulation , more than 1000 tons installing fixed equipment and installing more than 500 tons rotary equipment and installing around 300 tons structures,pre-commissioning electricity and in-struments utility and offsite
Client: Lorestan Petrochemical Co.
Contract type: Construction (C)
Startup year: 2014
Location: Khoramabad, Lorestan Province
Goals: To produce heavy and light linear and butane polyethylene